Design of the new bridge at Fierza Hydropower Plant

Client
KESH - Albanian Power Corporation (APC)

Period
12/2021 – 12/2022


Description
Our scope of work includes preparation of the preliminary and detailed design of the new bridge which will connect Fierza hydropower with the national road axis Fushe Arrez-Bajram Curri and demolition of the existing old bridge. This new bridge will be about 120 m length. The service includes:
- the dismantling of the old Drin River bridge at HEC Fierze.
- The detailed design for construction of a new bridge which will enable the crossing of the Drin River, since it is the only access possibility with HEC Fierzen and it is part of the Fushe Arres - Bajram Curri national road.
- Study and analysis for unblocking the water outlet channel from HEC Fierza, escaping the solid materials accumulated there.